|
|
|
|
|
 |
 |
 |
 |
 |
|
 |
 |
 |
 |
Knightsbridge Congestion Relief Project - Telecoms |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to building contractor. |
 |
 |
| Programme: |
3 years. |
 |
 |
| Systems: |
New PA, clocks, CCTV, digital video recording and help point system; Group control facilities with Green Park and Hyde Park. |
| |
 |
| Key Features: |
Integrated design and testing; Procurement; Software development; Engineering hours working practises; Control room changeover; Ergonomically designed control room desk; Acoustic modelling.
|
 |
 |
 |
 |
Jubilee Line Extension Project - C204 Tunnel Telephone |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build TT works; Subcontractor to telecoms contractor. |
 |
 |
| Programme: |
3 years. |
 |
 |
| Systems: |
Tunnel telephone. |
| |
 |
| Key Features: |
Installation of 48km of TT wire; Design, manufacture and installation of over 16,000 tunnel bracket pieces; Heavy use of works trains, possessions; Live TT changeovers. |
 |
 |
 |
 |
East London Line Long Line PA/CCTV Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Principal contractor to LUL. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
Line wide optical fibre backbone; Long line CCTV, long line PA, new local PA systems. |
| |
 |
| Key Features: |
Integrated design, building and testing of 9 racks; Software development; Installation of fibre cable within tunnel environment; Integration with existing local PA systems; Work in line control room. |
 |
 |
 |
 |
Mornington Crescent Station Refurbishment - Telecoms |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to building contractor. |
 |
 |
| Programme: |
10 months. |
 |
 |
| Systems: |
New PA, clocks, CCTV, help point system at English Heritage grade II listed London Underground station. |
| |
 |
| Key Features: |
Integrated design and testing; Procurement; Software development; Ergonomically designed control room desk; Listed buildings requirements. |
 |
 |
 |
 |
Bedford to Moorgate DOO CCTV Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build DOO CCTV; Principal Contractor to Network Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Installation of DOO CCTV at 44 Network Rail station platforms. |
| |
 |
| Key Features: |
Civil, mechanical and electrical design and construction; Operational changeovers; Possession management. |
 |
 |
 |
 |
Thameslink Rail Security Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build CCTV; Principal Contractor to Thameslink Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Installation of CCTV, help points and public address at 23 stations; New CCTV control centres at Luton and Tooting stations. |
| |
 |
| Key Features: |
Fast track installation programme; 250 new cameras; ISDN video transmission. |
 |
 |
 |
 |
Manchester Piccadilly Station PA, CCTV & CIS |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to M & E contractor. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
Design, procurement and commissioning, public address and CCTV. |
| |
 |
| Key Features: |
170 fixed & PTZ cameras; Digital recording; Section 12 PA system; 25 CIS displays; New staff control room with touch screen MMIs; Integrated design with M & E contractor; Acoustic modelling. |
 |
 |
 |
 |
Birmingham New Street Station PA and CCTV |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to M & E contractor. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
Design, procurement and commissioning public address and CCTV. |
| |
 |
| Key Features: |
248 fixed & PTZ cameras; Digital recording; Section 12 PA system, including Intellivox system; New staff control room with touch screen MMIs; Integrated design with M & E contractor. |
 |
 |
 |
 |
Signal Box Concentrator Renewals |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build SPT systems; Principal Contractor to Network Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Design, procurement, installation of telephone concentrators and PABXs. |
| |
 |
| Key Features: |
Installation of concentrators and PABXs at 15 signal boxes; Operational changeovers; Diversion of SPT circuitry; Transfer of block bells; 3 party testing; Handback procedures. |
 |
 |
 |
 |
Swindon to Uffington Cable Renewals |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build SPT systems; Principal contractor to Network Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Under track crossings (UTX); 30pr copper infrastructure; Networked concentrators; TDM & Reed signalling systems. |
| |
 |
| Key Features: |
Cable route clearance and refurbishment; Design and construction of 4 new UTX; Tiii possession management; Installation of 38km of line side cable; Installation of 2 concentrators and new signallers' SPT keypads; Operational changeovers of 60 SPTs; Third party testing; Handback procedures; TDM and Reed signalling circuits by approved subcontractor; SMTH update of source records. |
 |
 |
 |
 |
East London Line Tunnel Telephone System |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build tunnel telephone project; Principal Contractor to LUL. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Design, procurement, installation and testing of turnkey tunnel telephone systems. |
| |
 |
| Key Features: |
Design and procurement of 2 TT equipment racks;. Design and installation of tunnel wire support system; Track gauging; Installation of new line controller's TT panel. |
 |
 |
 |
 |
Station Limit Marker Board Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build construction; Principal Contractor to LUL. |
 |
 |
| Programme: |
5 months. |
 |
 |
| Systems: |
Design and construction of station limit marker signage at 181 LUL station platforms. |
| |
 |
| Key Features: |
Signage and bracket designed and installed for tunnel walls; Line clear and line safe procedures; Excavation and post installation in open sections; Procedures for Network Rail interface stations; In excess of 40 site operatives; Updating of LUL network CAD track and stations model. |
|
 |
Kings Cross
Redevelopment - Temporary Works |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design of temporary telecoms
systems; Subcontractor to Consultancy company |
 |
 |
| Programme: |
1 year |
 |
 |
| Systems: |
Design of telecoms, and
electrical, fire and mechanical aspects |
| |
 |
| Key Features: |
GRIP 4/5 lift and shift design
for Operational Control Room and CER relocation;
Interfaces with 6 separate construction packages,
management of stakeholders & incumbents |
 |
East London
Line - Decommissioning Works |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design, project management &
decommissioning; Principal contractor to Metronet
Rail |
 |
 |
| Programme: |
6 months |
 |
 |
| Systems: |
Design and decommission of
cameras, clocks, PA Systems, Lone Worker Alarm and
TT System |
| |
 |
| Key Features: |
Concept development and
compliance submission; implementation design;
post-closure operational arrangements plan;
co-ordination of maintainers and PFI contractors;
asset recovery and disposal |
 |
Kings Cross
Redevelopment – Permanent Works |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design of new station telecoms
systems; Prime Contractor to Network Rail |
 |
 |
| Programme: |
1 year |
 |
 |
| Systems: |
Design of CCTV, PA, PHP, Cat6
cabling , EACS, and CIS systems |
| |
 |
| Key Features: |
GRIP 4/5 Telecommunications
design interfacing with 6 separate construction
packages, acoustic modelling |
 |
Silverlink
Transfer Sites – Communications Design |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Concept studies for transfer of
13 former Silverlink Stations; Subcontractor to
building contractor |
 |
 |
| Programme: |
6 months |
 |
 |
| Systems: |
Asset survey and design of
communication systems including CIS, PA, CCTV, LLPA,
concentrator. |
| |
 |
| Key Features: |
Initial scooping of PFI
requirements; development of RIBA stage B report;
group control facility strategy; consultation with
incoming Ops Team; management of NR interface; CIS
strategy (combined LU/NR) |
 |
Ebbsfleet
CTRL Station – Communications Discipline |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Consultancy, project management
and installation for communications and Information
Services ;Sub-contractor to building contractor |
 |
 |
| Programme: |
6 months |
 |
 |
| Systems: |
Installation of CCTV; PA; PHP;
CIS; Cat6 cabling ; EACS; |
| |
 |
| Key Features: |
Short programme to ensure opening
of HS1, modification of base build design and
multi–user requirement scoping. |
 |
Rickmansworth and Moor Park Stations Communication
Discipline Design Service |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Survey, assurance, design;
Sub-contractor to Principal Consultant |
 |
 |
| Programme: |
9 months |
 |
 |
| Systems: |
Design and installation of PHP
and CCTV |
| |
 |
| Key Features: |
Concept design and compliance
submission; acoustic modelling; camera view surveys;
development of RIBA stage D to F design |
 |
 |
| Contract: |
Design and build telecoms;
Sub-contractor to Principal Contractor |
 |
 |
| Programme: |
1 year |
 |
 |
| Systems: |
All retail comms systems
including Information Management Control Systems |
| |
 |
| Key Features: |
Design installation and
commissioning; full integration into St. Pancras
International Station Control; up to 100 operatives
on site |
 |
Edinburgh
Waverley Station PA, CCTV and CIS |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms;
Subcontractor to M & E contractor. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
Design, procurement and
commissioning, public address and CCTV. |
| |
 |
| Key Features: |
60 fixed cameras; Digital
recording; 80 Loudspeaker PA system; 37 CIS
displays; Integrated design with M & E contractor. |
 |
 |
| Contract: |
Technical strategy for SOR
relocations; Principal contractor to Metronet Rail |
 |
 |
| Programme: |
18 Months |
 |
 |
| Systems: |
Manage technical and operational
aspects of SOR relocations |
| |
 |
| Key Features: |
Negotiation with asset engineers
and LU; Management of PFI contractors and 3rd
parties; programme development; Co-ordination of
client disciplines; Cable/asset ID surveys; Sites:
Piccadilly Circus, Bond Street, St. Paul’s etc |
 |
White City
Development – TT Modifications |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Turnkey Design & Build; Principal
contractor to Metronet Rail |
 |
 |
| Programme: |
9 months |
 |
 |
| Systems: |
Design, supply, installation,
commissioning |
| |
 |
| Key Features: |
Pre-implementation feasibility
study for ED approval; Turnkey tunnel telephone
system; provision of TT for overbuilt Central Line;
Possession Management |
 |
Liverpool
South Parkway Station PA, CCTV CIS & Telephony
System |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms;
Subcontractor to M & E contractor. |
 |
 |
| Programme: |
18 months. |
 |
 |
| Systems: |
Design, procurement and
commissioning of public address, CCTV, Help Points
and telephony system. |
| |
 |
| Key Features: |
110 fixed and PTZ cameras;
Digital recording; PA system; help points; long line
PA; Acoustic modelling; Integrated design with M & E
contractor. |
 |
|
|
 |
| © 2004-2008, Fourway Communication Ltd, UK |
|
| |
|
|
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
|
|