Knightsbridge Congestion Relief Project - Telecoms |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to building contractor. |
 |
 |
| Programme: |
3 years. |
 |
 |
| Systems: |
New PA, clocks, CCTV, digital video recording and help point system; Group control facilities with Green Park and Hyde Park. |
| |
 |
| Key Features: |
Integrated design and testing; Procurement; Software development; Engineering hours working practises; Control room changeover; Ergonomically designed control room desk; Acoustic modelling.
|
 |
 |
 |
 |
Jubilee Line Extension Project - C204 Tunnel Telephone |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build TT works; Subcontractor to telecoms contractor. |
 |
 |
| Programme: |
3 years. |
 |
 |
| Systems: |
Tunnel telephone. |
| |
 |
| Key Features: |
Installation of 48km of TT wire; Design, manufacture and installation of over 16,000 tunnel bracket pieces; Heavy use of works trains, possessions; Live TT changeovers. |
 |
 |
 |
 |
East London Line Long Line PA/CCTV Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Principal contractor to LUL. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
Line wide optical fibre backbone; Long line CCTV, long line PA, new local PA systems. |
| |
 |
| Key Features: |
Integrated design, building and testing of 9 racks; Software development; Installation of fibre cable within tunnel environment; Integration with existing local PA systems; Work in line control room. |
 |
 |
 |
 |
Mornington Crescent Station Refurbishment - Telecoms |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to building contractor. |
 |
 |
| Programme: |
10 months. |
 |
 |
| Systems: |
New PA, clocks, CCTV, help point system at English Heritage grade II listed London Underground station. |
| |
 |
| Key Features: |
Integrated design and testing; Procurement; Software development; Ergonomically designed control room desk; Listed buildings requirements. |
 |
 |
 |
 |
Bedford to Moorgate DOO CCTV Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build DOO CCTV; Principal Contractor to Network Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Installation of DOO CCTV at 44 Network Rail station platforms. |
| |
 |
| Key Features: |
Civil, mechanical and electrical design and construction; Operational changeovers; Possession management. |
 |
 |
 |
 |
Thameslink Rail Security Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build CCTV; Principal Contractor to Thameslink Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Installation of CCTV, help points and public address at 23 stations; New CCTV control centres at Luton and Tooting stations. |
| |
 |
| Key Features: |
Fast track installation programme; 250 new cameras; ISDN video transmission. |
 |
 |
 |
 |
Manchester Piccadilly Station PA, CCTV & CIS |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to M & E contractor. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
Design, procurement and commissioning, public address and CCTV. |
| |
 |
| Key Features: |
170 fixed & PTZ cameras; Digital recording; Section 12 PA system; 25 CIS displays; New staff control room with touch screen MMIs; Integrated design with M & E contractor; Acoustic modelling. |
 |
 |
 |
 |
Birmingham New Street Station PA and CCTV |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Subcontractor to M & E contractor. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
Design, procurement and commissioning public address and CCTV. |
| |
 |
| Key Features: |
248 fixed & PTZ cameras; Digital recording; Section 12 PA system, including Intellivox system; New staff control room with touch screen MMIs; Integrated design with M & E contractor. |
 |
 |
 |
 |
Signal Box Concentrator Renewals |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build SPT systems; Principal Contractor to Network Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Design, procurement, installation of telephone concentrators and PABXs. |
| |
 |
| Key Features: |
Installation of concentrators and PABXs at 15 signal boxes; Operational changeovers; Diversion of SPT circuitry; Transfer of block bells; 3 party testing; Handback procedures. |
 |
 |
 |
 |
Swindon to Uffington Cable Renewals |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build SPT systems; Principal contractor to Network Rail. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Under track crossings (UTX); 30pr copper infrastructure; Networked concentrators; TDM & Reed signalling systems. |
| |
 |
| Key Features: |
Cable route clearance and refurbishment; Design and construction of 4 new UTX; Tiii possession management; Installation of 38km of line side cable; Installation of 2 concentrators and new signallers' SPT keypads; Operational changeovers of 60 SPTs; Third party testing; Handback procedures; TDM and Reed signalling circuits by approved subcontractor; SMTH update of source records. |
 |
 |
 |
 |
East London Line Tunnel Telephone System |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build tunnel telephone project; Principal Contractor to LUL. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Design, procurement, installation and testing of turnkey tunnel telephone systems. |
| |
 |
| Key Features: |
Design and procurement of 2 TT equipment racks;. Design and installation of tunnel wire support system; Track gauging; Installation of new line controller's TT panel. |
 |
 |
 |
 |
Northern Line Trains Cabling Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Installation of cables and equipment; Subcontractor to telecoms contractor. |
 |
 |
| Programme: |
9 months. |
 |
 |
| Systems: |
M & E installation. |
| |
 |
| Key Features: |
Installation only team; Site supervision; 50+ operatives; Engineering hours working procedures. |
 |
 |
 |
 |
Kings Cross Station Escalator Renewals - Cable Diversion Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build telecoms; Contractor to SSL. |
 |
 |
| Programme: |
12 months. |
 |
 |
| Systems: |
Diversion of major telecoms cable route containing PA, clocks, CCTV, help points, telephones, etc. |
| |
 |
| Key Features: |
Cable surveying and tracing; Escalator machine chamber working procedures; Installation of new cable and containment; Over 40 nights of operational changeovers. |
 |
 |
 |
 |
Station Limit Marker Board Project |
 |
 |
 |
 |
 |
 |
 |
| Contract: |
Design & build construction; Principal Contractor to LUL. |
 |
 |
| Programme: |
5 months. |
 |
 |
| Systems: |
Design and construction of station limit marker signage at 181 LUL station platforms. |
| |
 |
| Key Features: |
Signage and bracket designed and installed for tunnel walls; Line clear and line safe procedures; Excavation and post installation in open sections; Procedures for Network Rail interface stations; In excess of 40 site operatives; Updating of LUL network CAD track and stations model. |
|
 |
|
|
 |